Oroville Spillways Phase 2 Update October 3, 2018

YouTube description:

On the upper chute of the main spillway, workers continue to place structural concrete sidewalls and install epoxy-coated rebar for concrete slabs. Crews continue covering underdrain piping with gravel between the hillside and the outer sidewalls. Roller-compacted concrete (RCC) continues to be placed on the southern half of the emergency spillway splashpad.